EIR Transformer Replacement
Electrical Infrastructure Refurbishment – Utilities
CLIENT
Pilbara Mining Client
PROJECT DESCRIPTION
The EIR Transformer Replacement project involved the upgrade of all onsite HV transformers/substations, converting the existing 11kV system to an updated 33kV HV system. This initiative was crucial for enhancing the efficiency and reliability of electrical infrastructure in the area.
EXECUTION
Direct involvement with the utilities division facilitated seamless execution of the project. Our team collaborated closely with stakeholders to ensure a smooth transition and minimal disruption during the upgrade process.
PROJECT DURATION
The project spanned over 7 years, from 2015 to August 2022, with the core transformation phase occurring between March 2023 and June 2023.
CHALLENGES & SOLUTIONS
Several challenges, including labor changes and engineering complexities, emerged during the project lifecycle. However, through proactive onsite support, effective management strategies, and direct communication with the client, we navigated through these obstacles with agility and professionalism.
Overall, the Tom Price EIR Transformer Replacement project stands as a testament to our expertise in electrical infrastructure refurbishment and our commitment to delivering high-quality solutions that meet the needs of our clients.
Tasman Power teams execute every project with utmost commitment to our core values of people, safety, exceptional skill, exemplary service, care, and common systems. These values guide our every action, ensuring that each endeavour is executed with precision, integrity, and a relentless dedication to delivering value – always!
HAVE A PROJECT IN MIND?
Contact us to discuss.